Hydraulic Oil Analysis for a Used Injection Moulding Machine
Check hydraulic oil reports before buying a used injection moulding machine. Match the sample to the press, find recent oil changes and agree when to retest.
Before paying a deposit on a used Haitian, YIZUMI or Chen Hsong press, ask for a hydraulic oil report tied to the machine’s serial number, the circuit sampled and the hours on that oil. A normal result can support your decision when you know how and when the sample was taken. If it came from recently replaced oil and the seller cannot document the operating time or provide earlier reports, make a repeat sample part of the inspection agreement.
This check is for hydraulic and servo-hydraulic machines in the 500–3,300 metric-tonne clamping force range. Confirm the model, generation, clamping force and original units from the machine documentation and nameplate. Identify the installed hydraulic system before agreeing which oil circuit to test.
Get the service timeline and sample record
- Match the report to the offered press. Ask for a nameplate photo, the original lab report and the bottle ID shown on the sampling record. Record the circuit, sampling point, date, machine hours, hours on the oil and the fluid product and grade. If the machine has a separate hydraulic circuit that matters to the intended job, ask whether it needs its own sample.
- Check what changed before the sample. Ask for the dates and operating hours of any oil change, significant top-up, filter replacement, flush or pump work. Request any earlier reports from that circuit. Phillips 66 advises against routine sampling immediately after an oil change or significant top-up. Chevron recommends recording machine and oil hours and sampling consistently when comparing results over time.
- Agree how the next sample will be obtained. Have a qualified technician agree on a safe, representative sample point and operating conditions with the machine maker’s documentation and the lab. Use the same point and method for a comparison. If the press is disconnected or there is no safe sampling access, put the deferred test, its acceptance criteria and the remedy for an adverse result in writing.
Decide what the report supports
| Report item | Check before accepting the result |
|---|---|
| Particle count and ISO 4406 code | Ask which cleanliness requirement applies to the installed circuit. Danfoss lists different requirements by component type and operating pressure. Agree the limit for the actual press from the applicable machine and component documentation. |
| Water and viscosity | Check the test methods, units and stated reference. Confirm that viscosity was compared with the specified fluid under the same test conditions. Have the technician investigate a confirmed deviation before acceptance. |
| Wear metals | Ask the lab to interpret the results alongside earlier comparable reports, oil hours and any system repairs. An elemental result may reflect the additive package, contamination or wear. Use the laboratory’s interpretation and the loaded test to assess whether component diagnosis is needed. |
When a clean report follows an oil change
Suppose the seller shows normal results for the correct serial number. The oil and filter were changed just before the sample and the report leaves the oil hours blank. Ask what prompted the change and request the work order and any earlier result. Keep the new report as evidence for the fluid sampled, then agree a repeat sample under documented operating conditions and a witnessed loaded run. Have the technician and lab set the resampling point and timing for that machine. If the same circuit shows a repeated abnormal finding, require diagnosis and an agreed retest before acceptance.
Pair the report with the Haitian Mars III warm-load check when assessing that series. Put the outstanding oil and hydraulic checks in the machine acceptance plan, with the responsible party and when the result is due.
Buyer questions
Can I accept a press that has no previous oil reports?
Ask for a witnessed representative sample and an agreed loaded trial. Record the result as the first documented sample and decide whether the remaining uncertainty warrants a purchase condition. There is no trend until you have comparable results over time.
Is a recent filter replacement a reason to reject the press?
Check whether it was scheduled service or a response to contamination or repair. Ask for the service date, reason for the work, parts fitted and any verification carried out afterwards. Then decide with your inspector whether the existing sample answers the outstanding condition question.
Browse GEEPOW’s used injection moulding machine sourcing page and enquire about a press for your project. Share your target clamping force, model or serial number if available, destination and the oil report or service records you want reviewed.